Microsoft 70-445 Real Exam Questions

TS: Microsoft SQL Server 2005 Business Intelligence – Development and Maintenance

This exam is intended for experts in implementing and maintaining solutions by using the Microsoft SQL Server 2005 Business Intelligence tool suite. The qualified candidate for this exam typically has the following experience or knowledge.

  • Knowledge of database schemas, both relational and multidimensional

  • Experience with and/or knowledge of implementing a cube in SQL Server Analysis Services (SSAS)

  • Experience with and/or knowledge of SSAS data mining algorithms

  • Experience creating and deploying SQL Server Reporting Services (SSRS) reports

  • Experience authoring and deploying SQL Server Integration Services (SSIS) packages

  • Experience working with the Microsoft .NET Framework

1: You are designing a Microsoft SQL Server 2005 Integration Services (SSIS) package.
The package has the following features:
         Two Data Flow tasks and two Control Flow tasks
         A success constraint between each Data Flow task and the subsequent Control Flow task
The package uses one transaction for all the tasks.
You need to configure the package so that the two Data Flow tasks use their own transactions. You also need to ensure that each Control Flow task is enlisted in the same transaction as its preceding Data Flow task.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
A.Change the TransactionOption property to Supported for the package.
B.Change the TransactionOption property to Required for the package.
C.Change the TransactionOption property to Supported for each Data Flow task.
D.Change the TransactionOption property to Required for each Data Flow task.
E.Change the TransactionOption property to Supported for each Control Flow task.
F.Change the TransactionOption property to Required for each Control Flow task.
Correct Answers: A D E

2: You are designing a Microsoft SQL Server 2005 Integration Services (SSIS) package. The package contains 30 Data Flow tasks and 30 Control Flow tasks. The package runs slower than expected. You need to capture the start time, the finish time, and the elapsed time for the validation and execution of the package. What should you do?
A.Enable the OnProgress event handler and use the Control Flow tasks to write the information to a log.
B.Monitor the Progress tab during the execution of the package, and then monitor the Execution Results tab.
C.Use the Performance Monitor tool to capture the counters from the SQL Server: SSIS Service object. Analyze the output for the required information.
D.Use the Performance Monitor tool to capture the counters from the SQL Server: SSIS Pipeline object. Analyze the output for the required information.
Correct Answers: B

3: Microsoft SQL Server Management Studio (SSMS) is installed on your workstation. Microsoft Business Intelligence Development Studio (BIDS) is not installed on your workstation.
You need to create a package that must meet the following requirements:
     It must be transactional.
     It must be optimized for 20 tables.
     It must be stored securely in the msdb database of a remote server.
What should you do?
A.Create the package by using DTS Designer.
B.Create the package by using the Package Migration Wizard.
C.Create the package by using the Microsoft SQL Server Import and Export Wizard.
D.On the Microsoft SQL Server 2005 Integration Services (SSIS) menu, click the Create Package submenu.
Correct Answers: C

4: You are designing a Microsoft SQL Server 2005 Integration Services (SSIS) package.
While testing, a Transact-SQL user-defined function causes duplicate key values that stop the transformation.
To permit the transformation to continue, the package must perform the following tasks:
1. Ascertain which rows are affected.
2. Insert the rows that fail into a table.
3. Continue with the process.
You need to change certain properties in the package to meet the requirements.
Which three tasks should you perform? (Each correct answer presents part of the solution. Choose three.)
A.Choose the Redirect Row option for the Error property on the key column.
B.Choose the Ignore Failure option for the Error property on the key column.
C.Choose the Fail Component option for the Error property on the key column.
D.Add a DataReader source to use a new Data Flow destination when the Failure constraint is fired.
E.Add a DataReader source to use a new Data Flow destination when the Completion constraint is fired.
F.Edit the Error Output properties for each DataReader source and configure each data source for error handling.
Correct Answers: A D F

5: You are designing a Microsoft SQL Server 2005 Integration Services (SSIS) package.
The package uses at least one sequence container in one transaction. Each transaction controls a Data Flow task and a Control Flow task. Each Data Flow task has a Success constraint.
The Control Flow task follows the Success constraint. The package must include the following requirements:
   Each Data Flow task must use its own transaction.
   The Control Flow task and the Data Flow task that precedes it must succeed or fail as an atomic unit.
   A restart point must restart each Data Flow task and the Control Flow task that follows it as an atomic unit.
You need to make changes in the control flow designer to meet the outlined requirements.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A.Add all the Data Flow tasks and the Control Flow tasks to one sequence container.
B.Add a sequence container for each Control Flow task and the Data Flow task that precedes it.
C.Change the FailPackageonFailure property to true for each new sequence container that is added to the package.
D.Change the FailPackageonFailure property to false for each new sequence container that is added to the package.
Correct Answers: B C

6: You are designing a Microsoft SQL Server 2005 Integration Services (SSIS) package.
The OLE DB data source for the package is a database that is updated frequently.
You need to create a package that accomplishes the following tasks:
    Implement the IRowsetFastLoad interface.
    Support various data flow destinations.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

A.Use an OLE DB data flow destination.
B.Use a Recordset data flow destination.
C.Use a DataReader data flow destination.
D.Create separate data flow destinations within the same Data Flow task.
Correct Answers: A D

7: You are designing Microsoft SQL Server 2005 Analysis Services (SSAS) cubes for two business units.
Each business unit has the following requirements:
       Full administrative access only to its own cubes and not to the cubes of the other unit.
       Ability to run its cubes on a different computer in the event of a hardware failure.
You need to install SSAS in a configuration to create cubes that meet the above requirements.
Which instance should you use?
A.Two clustered instances
B.A single clustered instance
C.Two nonclustered instances
D.A single nonclustered instance
Correct Answers: A

8: You are developing a Microsoft SQL Server 2005 Analysis Services (SSAS) solution by using Business Intelligence Development Studio (BIDS). The SSAS instance runs under a local system account. A trust relationship exists between the machine that hosts the SSAS instance and the data source. You need to use the Impersonation Information dialog box to create a data source that SSAS can connect to when SSAS is deployed from any workstation. Which impersonation information should you use?
A.Default
B.Service account
C.Credentials of the current user
D.Specific user name and password
Correct Answers: D

Download  |  Password: certificatexam.com